SET MEMBERSHIP LIST
All Technologies (TCH+SRCENCP)
Technologies: Demand (DMD)
TIME SERIES DATA 1990 2000 2010 2020 2030 2040 2050
Bound on capacity 50 106.25 162.5 218.75 275 331.25 387.5
Upper (unit/annum)
Annual utilisation 1 1 1 1 1 1 1
(-)
Annual delivery cost 0.5 0.5 0.5 0.5 0.5 0.5 0.5
Gas for industry [GJ] (1995 EURO(ECU)/unit)
Technical efficiency 0.9 0.9 0.9 0.9 0.9 0.9 0.9
(-)
Annual fixed O&M cost 1.59 1.59 1.59 1.59 1.59 1.59 1.59
(1995 EURO(ECU)/unit/annum)
Total cost of investment in new capacity 26.5 26.5 26.5 26.5 26.5 26.5 26.5
(1995 EURO(ECU)/unit/annum)
Energy carrier input: demand technology 0.45 0.46 0.47 0.47 0.47 0.47 0.47
Energy saving [GJ] (-)
Energy carrier input: demand technology 0.55 0.54 0.53 0.53 0.53 0.53 0.53
Gas for industry [GJ] (-)
End-use demand output 1 1 1 1 1 1 1
LTH small industry (-)
TIME INDEPENDENT DATA TID
Units of activity/unit of capacity 1
(-)
Lifetime of new capacity 20
(number of years)
Start year 1990
(calendar year)