SET MEMBERSHIP LIST
All Technologies (TCH+SRCENCP)
Technologies: Conversion (CON)
Technologies: Conversion: Electric, Not District Heat (ELE)
Technologies: Conversion: Centralised (CEN)
Technologies: Conversion: Standard (not BAS/NLM)
Technologies: Conversion/Demand/Process: Renewable (RNT)
TIME SERIES DATA 1990 2000 2010 2020 2030 2040 2050
Annual availability 0.7 0.7 0.7 0.7 0.7 0.7 0.7
(decimal fraction)
Bound on capacity 0.78 0.85 0.85 0.85 0.85 0.85 0.85
Lower (gigawatts)
Bound on capacity 0.79 0.86 1.1 1.35 1.6 1.845 2.085
Upper (gigawatts)
Annual fixed O&M cost 26 26 26 26 26 26 26
(1995 EURO(ECU)/gigawatts)
Energy carrier input: conversion technology 6 6 6 6 6 6 6
Geothermal heat [GJ] (petajoules/petajoules)
Total cost of investment in new capacity 1030 1030 1030 1030 1030 1030 1030
(1995 EURO(ECU)/gigawatts)
Fraction of capacity in peak equations 0 0 0 0 0 0 0
(decimal fraction)
Residual installed capacity 0.75 0.4 0 0 0 0 0
(gigawatts)
TIME INDEPENDENT DATA TID
Fraction of unavailability which is forced outage 1
(decimal fraction)
Units of activity/unit of capacity 31.536
(petajoules/gigawatts)
Lifetime of new capacity 30
(number of years)
Electricity output 1
Electricity (decimal fraction)
Start year 1990
(calendar year)