SET MEMBERSHIP LIST
All Technologies (TCH+SRCENCP)
Technologies: Process (PRC)
Technologies: Process: Standard (PRE)
TIME SERIES DATA 1990 2000 2010 2020 2030 2040 2050
Annual availability 1 1 1 1 1 1 1
(-)
Bound on capacity 0.0001 0.000213 0.000325 0.000438 0.00055 0.000663 0.000
Lower (unit)
Annual delivery cost 4.8 4.8 4.8 4.8 4.8 4.8 4.8
Gas for commercial sector [GJ] (1995 EURO(ECU)/unit)
Annual fixed O&M cost 0.55 0.55 0.55 0.55 0.55 0.55 0.55
(1995 EURO(ECU)/unit/annum)
Energy carrier input: process technology 1.031 1.020667 1.010333 1 1 1 1
Gas for commercial sector [GJ] (petajoules/unit)
Total cost of investment in new capacity 11.05 11.05 11.05 11.05 11.05 11.05 11.05
(1995 EURO(ECU)/unit/annum)
Material output: process technology 1 1 1 1 1 1 1
COMMERCIAL HEAT, NORTH EUROPE [GJ] (unit of volume for MVOs/unit)
TIME INDEPENDENT DATA TID
Units of activity/unit of capacity 1
(-)
Lifetime of new capacity 15
(number of years)
Start year 1990
(calendar year)